Disertación de Maestría
DOI
https://doi.org/10.11606/D.18.2008.tde-16072008-104640
Documento
Autor
Nombre completo
Thays Josyane Perassoli Boiko
Dirección Electrónica
Instituto/Escuela/Facultad
Área de Conocimiento
Fecha de Defensa
Publicación
São Carlos, 2008
Director
Tribunal
Moccellin, João Vitor (Presidente)
Nagano, Marcelo Seido
Toledo, Franklina Maria Bragion de
Título en portugués
Métodos heurísticos para a programação em flow shop permutacional com tempos de setup separados dos tempos de processamento e independentes da seqüência de tarefas
Palabras clave en portugués
Flow shop permutacional
Programação da produção
Tempos de setup
Resumen en portugués
Este trabalho dedica-se ao problema de programação em flow shop permutacional com tempos de setup separados dos tempos de processamento e independentes da seqüência de execução das tarefas com o objetivo de minimizar a duração total da programação (Makespan). Por intermédio de investigações realizadas sobre as características estruturais do problema de programação e sua solução, uma propriedade deste problema é apresentada. Esta propriedade, denominada "Propriedade LBY", considerando quaisquer duas tarefas adjacentes Ju e Jv (Ju imediatamente precede Jv) independentemente de suas posições na seqüência de tarefas, fornece, um limitante inferior do tempo de espera para a tarefa Jv entre o fim do seu processamento na máquina Mk e o início do seu processamento na máquina seguinte. Dois novos métodos heurísticos são desenvolvidos, com base na propriedade apresentada e no procedimento de inserção de tarefas dos conhecidos métodos N&M e NEH: um construtivo, denominado BMc; e, um melhorativo, denominado BMm. Os métodos heurísticos propostos são comparados com os métodos heurísticos melhorativos de Cao; Bedworth (1992) e Rajendran; Ziegler (1997), através de um grande número de problemas gerados aleatoriamente. Os tempos de processamento são distribuídos no intervalo [1, 99] e os tempos de setup nos intervalos de [1, 49], [1, 99], [51, 149] e [101, 199]. Os métodos são avaliados quanto à porcentagem de sucesso em obter a melhor solução, ao desvio relativo médio e o tempo médio de computação. Os resultados da experimentação computacional mostram a qualidade do método construtivo BMc e a melhor performance do método melhorativo BMm. Estes resultados são apresentados e discutidos.
Título en inglés
Heuristic methods for the permutation flow shop scheduling problem with separated, non-batch, and sequence-independent setup times
Palabras clave en inglés
Permutation flow shop
Production scheduling
Setup times
Resumen en inglés
This work addresses the permutation flow shop scheduling problem with separated, non-batch, and sequence-independent setup times with the objective of minimizing the total time to complete the schedule (Makespan). Following an investigation of problem structural characteristics and your solution a property of this scheduling problem is presented. This property, denoted by "Property LBY", given any two adjacent jobs Ju e Jv (Ju immediately precedes Jv), regardless of their position in the sequence of jobs, provides an lower bound of the waiting time for job Jv between the end of its operations on the machine Mk and the beginning on machine M(k+1). Two news heuristics methods are development, on the basis of the presented property and in the job insertion procedure of the known methods named N&M and NEH: one constructive, denote by BMc; and, one improvement, denote by BMm. The proposed heuristics methods are compared with the improvement heuristics methods of Cao; Bedworth (1992) and Rajendran; Ziegler (1997), by a large number of randomly generated problems. The processing time are sampled from a distribution ranging from [1, 99] and, the setup times are sampled from distributions ranging from [1, 49], [1, 99], [51, 149] and [101, 199]. The methods are evaluated by the percentage of success in find the best solution, the average relative deviation and the average computation time. The results of the computational investigation show the quality of the constructive heuristic method BMc and that the improvement heuristic method BMc outperforms all others. These results are presented and discussed.
 
ADVERTENCIA - La consulta de este documento queda condicionada a la aceptación de las siguientes condiciones de uso:
Este documento es únicamente para usos privados enmarcados en actividades de investigación y docencia. No se autoriza su reproducción con finalidades de lucro. Esta reserva de derechos afecta tanto los datos del documento como a sus contenidos. En la utilización o cita de partes del documento es obligado indicar el nombre de la persona autora.
Fecha de Publicación
2008-07-18
 
ADVERTENCIA: Aprenda que son los trabajos derivados haciendo clic aquí.
Todos los derechos de la tesis/disertación pertenecen a los autores
CeTI-SC/STI
Biblioteca Digital de Tesis y Disertaciones de la USP. Copyright © 2001-2024. Todos los derechos reservados.