Thèse de Doctorat
DOI
https://doi.org/10.11606/T.18.2011.tde-05092011-094838
Document
Auteur
Nom complet
Fabio José Ceron Branco
Adresse Mail
Unité de l'USP
Domain de Connaissance
Date de Soutenance
Editeur
São Carlos, 2011
Directeur
Jury
Nagano, Marcelo Seido (Président)
Azzolini Júnior, Walther
Cazarini, Edson Walmir
Oliveira, Marcio Mattos Borges de
Ribeiro, José Francisco Ferreira
Titre en portugais
Um novo método heurístico construtivo de alto desempenho para o problema noidle flow shop
Mots-clés en portugais
Makespan
Métodos heurísticos
No-idle
Programação da produção
Programação flow shop permutacional
Resumé en portugais
Este trabalho é direcionado ao problema de Programação de Operações No-Idle Flow Shop Permutacional. Uma propriedade do problema, oriunda de estudo sobre a sua característica, é apresentada e utilizada para o desenvolvimento de um novo método heurístico construtivo, com o objetivo de minimizar a Duração Total da Programação (makespan). O novo método é comparado com os melhores heurísticos construtivos reportados na literatura, conhecidos por IG, KK e FRB3. Os resultados da experimentação computacional mostraram o melhor desempenho do método proposto, denominado BHBN, para os problemas testes de Ruiz et al. (2008) e Taillard (1993), quanto à qualidade da solução, apresentando também eficiência computacional.
Titre en anglais
A new constructive heuristic method for high performance in no-idle flow shop problem
Mots-clés en anglais
Flow-shop sequencing
Heuristics
Makespan
No-idle
Production scheduling
Resumé en anglais
This work is addressed to the No-Idle Flow Shop Sequencing problem. As a result of an investigation on the problem characteristics it is presented a property of this scheduling problem, which is used for the development of a new constructive heuristic with the objective of minimizing the Total Time to complete the schedule (makespan). The new method is compared with the best constructive heuristics reported in the literature, named IG, KK and FRB3. Results from computational experience showed the best performance of the proposed method, denoted by BHBN, for the instances of Ruiz et al. (2008) and Taillard (1993), as to the quality of the solution, and also computational efficiency.
 
AVERTISSEMENT - Regarde ce document est soumise à votre acceptation des conditions d'utilisation suivantes:
Ce document est uniquement à des fins privées pour la recherche et l'enseignement. Reproduction à des fins commerciales est interdite. Cette droits couvrent l'ensemble des données sur ce document ainsi que son contenu. Toute utilisation ou de copie de ce document, en totalité ou en partie, doit inclure le nom de l'auteur.
Date de Publication
2011-09-09
 
AVERTISSEMENT: Apprenez ce que sont des œvres dérivées cliquant ici.
Tous droits de la thèse/dissertation appartiennent aux auteurs
CeTI-SC/STI
Bibliothèque Numérique de Thèses et Mémoires de l'USP. Copyright © 2001-2024. Tous droits réservés.